Building and Construction Industry Payments Act (2004) (the Act)
The Security Of Payment Act in QLD creates a statutory entitlement for a Claimant to be paid for construction work that has been carried out or construction related goods and services that have been supplied to a Respondent.
By the provision of a Payment Claim and having it adjudicated under the Act.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
The Security Of Payment Act covers ‘Construction Work’ which is basically all building and related trades that are carried out for anybody that is not a resident home owner.
The Act also covers ‘Construction related goods and services’, if they have been provided by a supplier (such as a wholesaler) or person who provides services (such as a designer) if supplying or working for anybody that is not a resident home owner.
Note: The act does not cover mining work.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
You should provide a Payment Schedule within 10 business days.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
A Payment Claim must:
(a) Identify the construction work (or related goods and services) to which the progress payment relates,
(b) Indicate the amount of the progress payment that the claimant claims to be due (the 'claimed amount'), and
(c) State that it is made under this Act.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
A Payment Schedule is a document that indicates what the Claimant is to be paid by the Respondent.
A Payment Schedule must:
(a) Identify the Payment Claim to which it relates, and
(b) Indicate the amount of the progress payment that the Respondent proposes to make, and
(c) If the Respondent proposes to pay less than the claimed amount state the reasons for withholding payment.
A Payment Schedule requires all of these 3 items or it is not a Payment Schedule.
A Payment Schedule can be served by post, fax, email or hand-delivery.
Note: The Respondent’s position will be limited by the Payment Schedule. If you have any doubt about the application of Security Of Payments Act QLD, advice should be sought when preparing the Payment Schedule.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
If you did not provide a Payment Schedule the Claimant needs to wait until the due date for payment of its Payment Claim to pass and submit a notice under Section 21 (2) of the Security Of Payment Act. Once you receive this notice you have 5 business days to provide a Payment Schedule.
Have a question? Email us or ring 1300 76 86 30 for an outcome.
If you have provided a Payment Schedule and the Claimant still thinks that they are entitled to be paid they may make an Adjudication Application.
If they do you will be notified by the Adjudicator and given an opportunity to provide an Adjudication Response.
Note: The contents of the Adjudication Response are limited by the Payment Schedule.
In reality if you owe the Claimant money for construction work that has been carried out you should pay them.
However, if you legitimately feel that you are being inappropriately charged or over charged there are ways of maximising your opportunities and minimising risks.
Have a question? Email us or ring 1300 76 86 30 for an outcome.

The Building and Construction Industry Payments Act is undergoing significant changes at the moment.
If you have any questions, please call 1300 76 86 30 or email us.